What action should be taken if you encounter underground utility lines while digging?

  1. Continue working cautiously

  2. Immediately stop work and assess the situation

  3. Mark the area and resume digging

  4. Contact utility companies before continuing

The correct answer is: Immediately stop work and assess the situation

When encountering underground utility lines while digging, the best course of action is to immediately stop work and assess the situation. This approach prioritizes safety, allowing the operator to evaluate the potential risks involved with cutting or disturbing utility lines such as gas, water, electricity, or telecommunications. Stopping work ensures no unintended damage occurs to the utility lines which could lead to hazardous situations, including leaks, power outages, or injuries. Additionally, taking the time to assess the situation allows for a better understanding of the exact location and depth of the utility lines in relation to your digging operation. It also provides the opportunity to consult any available plans or documents related to the utility lines and may necessitate contacting utility companies to ensure proper procedures are followed before resuming work. This step is essential in minimizing risks and adhering to safety regulations.